Yellowstone’s Mo Brings Plenty Takes on Ohio’s Water-Hungry Data Centers

Yellowstone actor joins Piqua residents fighting a hyperscale facility that opponents claim could use 2 million gallons daily

Nikshep Myle Avatar
Nikshep Myle Avatar

By

Image: X/@WallStreetApes

Key Takeaways

Key Takeaways

  • Actor Mo Brings Plenty opposes a Piqua, Ohio hyperscale data center over water concerns.
  • Opponents claim the facility could consume up to 2 million gallons of water daily.
  • Grassroots group Save Piqua pursues a legal injunction as Ohio ranks sixth nationally for data centers.

A city council chamber in Piqua, Ohio, is nobody’s idea of a Hollywood set. But when Mo Brings Plenty — the actor who plays Mo on Yellowstone — stepped up to the mic recently, the room commanded the kind of attention usually reserved for zoning meetings about absolutely nothing. His target: a proposed hyperscale data center that opponents say could drain the community’s water supply at an industrial scale.

The Fight on the Ground

Piqua residents aren’t waiting for permits to start pushing back.

  • Opponents claim the proposed facility could consume up to 2 million gallons of water per day, according to stopohiodatacenters.org — though that figure has not been confirmed by project permitting documents and exceeds independent estimates for comparable facilities.
  • A June 2026 Ohio Chamber of Commerce study, reported by the Columbus Dispatch, found Ohio is “not facing an imminent water-supply shortage” from data center operations — but acknowledged the state “must build trust” with affected communities.
  • The grassroots group Save Piqua has hired legal counsel and is pursuing an injunction to block construction, according to WHIO-TV.

The water claim deserves scrutiny in both directions. One Ohio-focused analysis pegged a 100-megawatt hyperscale facility at around 528,000 gallons daily — well under the 2 million figure opponents cite. Whether Piqua’s project is larger, or the opponent estimate overstated, remains unclear without public permitting records. That ambiguity is itself the problem.

The Ohio Chamber’s own framing is telling: even industry advocates concede that “trust-building” is essential, per the Columbus Dispatch report. When your own cheerleaders admit a credibility gap exists, the gap is real.

Bigger Than One Town

Mo Brings Plenty is the hook, but the infrastructure pipeline is the story.

Ohio ranks sixth nationally for data center concentration. The AI and cloud computing boom is printing facilities across the state like a streaming service dropping seasons — fast, relentless, and often before anyone in town gets a meaningful say. Mo’s presence guarantees cameras and headlines. Without his involvement, this story lives and dies in municipal meeting minutes.

Save Piqua’s injunction effort is the next domino to watch. If it succeeds, expect it to become a template for communities from Ohio to Virginia asking a basic question: who decides what happens to your water when the servers move in?

That question still doesn’t have a clean answer. Permitting details remain opaque, the water figures unverified by official project documents, and the seat at the table for residents conspicuously small. The next move belongs to the courts — and to whoever finally releases the numbers.

Share this

At Gadget Review, our guides, reviews, and news are driven by thorough human expertise and use our Trust Rating system and the True Score. AI assists in refining our editorial process, ensuring that every article is engaging, clear and succinct. See how we write our content here →