Four hundred and seventy-four gigawatts. That’s the combined power demand sitting in ERCOT’s interconnection queue right now — roughly five times the Texas grid’s all-time peak demand record. Governor Greg Abbott has responded by announcing a moratorium on data center grid approvals while the Public Utility Commission of Texas and ERCOT audit the mountain of proposed projects. AI infrastructure ambition just ran headfirst into physical reality.
The Audit Nobody Answered
Only 28 of 377 companies bothered to submit required disclosures — and that ratio tells you everything.
The PUCT asked 377 data center companies for information covering tax breaks, power consumption, water use, cooling operations, community impact measures, and facility ownership. At the time of reporting, 28 had responded. Abbott stated that projects failing to comply with PUCT, ERCOT, and state law requirements should be denied grid connection entirely.
Here’s what the queue actually looks like:
- More than 1,800 projects await ERCOT approval; 90% are data centers
- Combined demand requested: 474 gigawatts
- Only 28 of 377 companies submitted required audit information
- Projects outside ERCOT’s jurisdiction (like El Paso) or those bringing their own power generation are unaffected
- Multiple local Texas jurisdictions have already enacted their own moratoriums and bans
ERCOT’s long-range forecasts through 2030 show data centers becoming the dominant factor in load planning. You don’t need to be a grid engineer to see the problem: it’s the equivalent of a city’s water authority receiving permit applications for five cities’ worth of daily consumption — with no new reservoir planned.
Some developers reportedly plan to sidestep the queue entirely by building behind-the-meter generation, essentially bringing their own power plant to the party. Critics argue the moratorium doesn’t go far enough and want formal legislation. Supporters call it a necessary check on unchecked buildout.
Neither side is wrong. That’s the problem.
Speed Bump or Guardrail?
The biggest question is whether this audit becomes durable regulation or just another terms-and-conditions checkbox that everyone clicks past.
How strict will the review actually be? How long does it last? Nobody has answered those questions publicly yet. Independent grid analysts note that without clear enforcement teeth, disclosure requirements alone rarely slow a pipeline of this scale — they add paperwork before approvals quietly resume. The moratorium could reshape how Texas handles large-load customers for years, or it could simply be a speed bump dressed as a guardrail.
What happens next determines whether Texas built a real framework covering power, water use, and community impact — or just bought time. The queue isn’t getting shorter.





























