Data Center Drains 30 Million Gallons Of Water, While Residents Face Restrictions

QTS facility consumes water worth $147,474 without payment while Fayette County residents endure conservation measures

C. da Costa Avatar
C. da Costa Avatar

By

Image: NARA & DVIDS Public Domain Archive – GetArchive

Key Takeaways

Key Takeaways

  • QTS data center consumed 30 million gallons without paying during billing oversight
  • Company faced zero fines despite violating peak usage restrictions during drought
  • Resident complaints about water pressure triggered discovery of $147,474 unpaid bills

Low water pressure in your shower hits differently when you discover the cause. Residents of Annelise Park, an upscale Fayetteville subdivision, complained about weak flows in 2025, triggering a county investigation that uncovered something infuriating: QTS, a Blackstone-owned data center developer, had consumed nearly 30 million gallons of water—equivalent to 44 Olympic-sized swimming pools—without paying a dime.

The massive 615-acre facility, one of America’s largest data center campuses, operated undetected by utility meters for approximately 4-15 months.

The Billing “Mix-Up” That Cost Six Figures

QTS racked up $147,474 in unpaid water bills during the metering blackout. The company blamed temporary construction activities like dust suppression and site preparation for the astronomical usage. Once operational, QTS claims its “closed-loop” cooling system will use minimal water—equivalent to just four households monthly.

Fayette County Water Director Vanessa Tigert attributed the oversight to staff shortages and procedural errors during transition to cloud-based metering systems.

No Penalties for Peak Violator

Despite breaking peak usage restrictions, QTS faced zero fines. “They’re our largest customer, and we have to be partners,” Tigert explained. “It’s called customer service.” UCLA’s Gregory Pierce found the leniency suspicious: “I don’t know exactly what’s happening here, but they probably don’t want to upset one of their new and largest customers.”

The facility generates tens of millions in annual property taxes—revenue that apparently outweighs conservation enforcement.

Facebook Fury Ignites Political Backlash

The scandal erupted when a resident’s public records request revealed the May 2025 discovery letter, which quickly spread across neighborhood Facebook groups. The timing stung: locals had been asked to conserve water and stop irrigating lawns while QTS topped monthly consumption charts.

Attorney James Clifton, running for county commissioner, slammed officials for “targeting citizens over the data center.” Fayetteville’s city council banned new data centers entirely last month.

Drought Meets Data Center Boom

Georgia leads the nation with more than 200 data centers, attracted by cheap electricity and tax incentives. Meta’s Newton County facility alone consumes 10% of the county’s water supply daily. The QTS incident coincided with Governor Kemp’s emergency drought declaration and statewide wildfire alerts.

Large data centers can consume 200 million gallons annually—enough water for roughly 2,000 homes. The QTS scandal reveals how rapidly expanding AI infrastructure collides with local resource limits. Other communities hosting data center developments now face a sobering question: will their utilities catch billing failures before residents lose water pressure, or only after the damage goes viral on social media?